Consenting at speed

Research

What the July 2026 reforms changed at the front end of the Development Consent Order regime, checked against primary law and read against 154,723 published DCO documents.

Aerial view of a solar farm in rolling countryside

How we approached it

Check the change against the source, and then look at how the regime actually runs before deciding where the effort should go.

Status
Research, with supporting tools
Purpose
Give promoters a checked statement of what changed and an evidence base on how DCOs actually run
Sector
Roads, rail, ports, airports, power generation including nuclear, power lines, pipelines, reservoirs, water and waste
Scope
The DCO regime in England and Wales
154,723
Published DCO documents downloaded and classified
54
Standard document types, from 107,000 free-text labels
61%
Of published documents belong to the examination stage

How we went about it

What changed in July 2026

The reforms rewrote the front end of the regime and left the rest of it in place.

On 24 July 2026 the Planning and Infrastructure Act 2025 changed the front end of the Development Consent Order regime. Six statutory pre-application provisions of the Planning Act 2008 went (ss.42, 43, 44, 45, 47 and 49), and with them the Statement of Community Consultation, the Consultation Report and the duty to publish preliminary environmental information before finalising the Environmental Statement. The acceptance test was rewritten, and a 10% biodiversity net gain requirement applies to applications made on or after 2 November 2026.

The pre-application duties, after 24 July 2026

s.42Consult prescribed consulteesOmitted
s.43Which local authorities to consultOmitted
s.44Which land interests to consultOmitted
s.45Timetable for consultationOmitted
s.46Notify the Secretary of State and host authoritiesRewritten
s.47Consult the local communityOmitted
s.48Publicise the proposed applicationSurvives
s.49Take account of responsesOmitted
Planning Act 2008, Part 5 Chapter 2, as amended by the Planning and Infrastructure Act 2025 (ss.5 and 6), in force 24 July 2026 (SI 2026/641). Section 48 keeps its publicity duty; its subsection (2) was omitted. Checked on legislation.gov.uk on 25 October 2026.

What acceptance now tests

Must be metThe s.46 notification was givenWithout it the application cannot be accepted (s.55(3)(ca)). The basic tests also remain: it is an application for development consent, and consent is needed.
Weighed in deciding whether the standard is satisfactory
  • ContentThe application form and accompaniments (s.37(3) to (5))
  • PublicityThe applicant's approach to s.48
  • AdviceRegard to the Inspectorate's s.51 advice
  • GuidanceRegard to guidance under s.50(1)
Planning Act 2008, s.55(3) to (4A), as substituted by the Planning and Infrastructure Act 2025, s.7, in force 24 July 2026 (SI 2026/641, with transitional provision in reg 6). Whether a promoter consulted adequately is no longer part of the test. Checked on legislation.gov.uk on 25 October 2026.

How the reforms arrived in 2026

  1. Costs power and compulsory purchaseThe Examining Authority can award costs (s.96B). The first compulsory purchase changes take effect.
  2. Biodiversity gain machinerySchedule 2A to the Planning Act 2008 in force (SI 2026/492): a gain objective of at least 10%.
  3. Biodiversity gain statementsDefra publishes the statements that set the objective for each infrastructure type.
  4. The main packagePre-application duties omitted; s.46 and the s.55 acceptance test rewritten (SI 2026/641).

Not yet in force Post-consent changes to Orders (Planning and Infrastructure Act 2025, s.12), and temporary possession of land (s.112, which waits on s.18 of the Neighbourhood Planning Act 2017).

Sources: legislation.gov.uk (Planning Act 2008 s.96B and Sch 2A; Planning and Infrastructure Act 2025 ss.12, 105, 112 and 118; SI 2026/641), checked 25 October 2026; Defra biodiversity gain statements for NSIPs, 2 June 2026. Compulsory purchase changes in force from 18 February: ss.105, 107, 110, 111 and 114; s.106 in part; ss.108 and 109 await regulations.

How the work was built

Four pieces of work, all of them built from public sources.

DCO ExplorerEvery published NSIP document, downloaded and sorted into 54 standard document types, then modelled as a knowledge graph across projects, organisations, document types and examination stages. 138,877 documents are classified at high confidence.
DCO Cost EstimatorA driver-based model of what it costs to take a scheme through consent, built on land interests, local planning authorities, consenting bodies, Environmental Statement chapters and representations, with design maturity and regime certainty as judgement levers. It is a structured judgement rather than a quotation.
The 2026 reforms, checkedWhat was removed, what survived, what is new and what is still to come, with the section, instrument and date behind each point.
A reference corpus252 documents: legislation, statutory instruments, every designated National Policy Statement, 26 judgments and current Planning Inspectorate guidance and advice, verified against source on 30-31 July 2026.

The tools sit alongside Project:OS, which sets out consenting as nine connected sub-processes, from consenting strategy and route selection through examination support, consent conditions and secondary consents to capturing precedent for the next scheme.

What the record shows

Examination is a spike rather than a curve. 61% of all published DCO documents belong to the examination stage, so that is the resourcing peak to plan for. The reforms do not move it: the examination timetable, the decision tests and the judicial review window are unchanged.

The change is all at the front end, where the consultation record is no longer a compliance document but a judgement a promoter may later have to defend. We also found no published benchmark for DCO consenting cost in any sector, which is why the Cost Estimator shows its evidence for each coefficient.

Where the documents are produced: 154,723 published DCO documents by stage

Examination stage61%
The application itself20%
Everything else19%
Source: DCO Explorer (July 2026), Synaform's classification of every published NSIP document by stage. "Everything else" is the remainder: decision, pre-examination, post-decision, pre-application and documents with no stage recorded.

The examination peak: documents published per scheme each month

Examination opensTypical closeTypical decision
-15-12-9-6-30+3+6+9+12+15+18+21+24

Months before and after the examination opened

Average across 107 schemes with a dated examination, aligned on the month each examination opened. DCO Explorer, data to July 2026. During examination a scheme publishes about 2.5 times as many documents a month as in the six months before; the typical examination closes six months after opening and the decision follows about six months later.

What the documents are: the eight largest of 54 types

Environmental Statement27,767
Plans and drawings18,405
Other or unclassified16,237
Responses to written questions9,140
Responses to Secretary of State consultation8,243
Comments on submissions7,936
Statements of common ground7,301
Additional submissions7,224
Documents by standard type, where "Other or unclassified" is the catch-all that is still being refined.

Where they come from: documents by sector

Generating stations (95 projects)81,711
Highways (30)33,745
Electric lines (21)12,762
Airports (4)8,043
Rail freight interchanges (5)5,225
Other pipelines (7)4,726
Harbour facilities (3)2,159
Generating stations, including wind, solar and nuclear, produce over half of all published documents.

Who a promoter will meet: organisations in the most projects

Natural England134
Environment Agency123
Historic England116
The Planning Inspectorate98
National Highways68
Number of projects in which each organisation submitted documents, out of 179 analysed. The same statutory bodies appear on most schemes, whatever the sector.

Skipping engagement does not make the objections go away; it moves them to examination, or to a challenge of the granted Order, where they are harder and more expensive to deal with.

What we cannot tell you yet

The reforms are recent, and the evidence on their effect simply does not exist yet.

  • No reformed application yet. As at 31 August 2026 we had identified no application accepted after the complete reformed pre-application route.
  • Time saved is a forecast. The government's expectation of about twelve months saved is a forecast, not a result.
  • Commencement is still moving. Provisions are commencing in tranches, so check the current position before relying on any of them.
  • What the corpus covers. 154,723 published documents across 268 projects, from 17,108 organisations. The charts analyse 179 projects in detail; 83 are excluded because they were decided or withdrawn before 2018, hold fewer than five documents, or are minimal legacy records (2,083 documents in all).
  • How the types were made. About 107,000 different free-text document labels were sorted into 54 standard types by a language-model classifier. 138,877 documents (89.8%) were classified at high confidence, 4.1% at medium and 6.1% at low; the lower-confidence share should be read with that in mind.
  • Cost is a structured judgement. The Cost Estimator is not a quotation. Design maturity and regime certainty are judgement levers, and its coefficients rest on the evidence it shows.
  • A dated corpus. The reference corpus was verified against source on 30-31 July 2026. Later guidance, instruments and judgments are not reflected until it is updated.

Talk to us about a scheme heading into consent

If a scheme is heading into consent under the reformed regime, we can help set out what has changed and where the effort is likely to fall.